Close
On the road
WebCam
Travel info
Toll
Motorway user service
HGV parking areas
Special transports
Summer traffic
The company
About us
History
Charter of services
Privacy
The motorway
Infrastructure
Technical information
Structure monitoring and maintenance
Projects
Road safety
Traffic management
The Traffic Managers
Winter road service
Emergencies
Sustainability
Hydrogen
Electric
Road-rail intermodality
Photovoltaic
European projects
Areas of intervention
Sensors and Security
European projects
MENU
en
it
de
en
en
it
de
en
FOR TRAFFIC INFO AND NOTIFICATIONS
traffic control centre - CAU
+390461980085
800 279940
toll-free number from Italy
800 22022022
toll-free number from Germany, Austria, Holland
FOR GENERAL INFORMATION
+390461212611
2
There is/are n°2 announcement/s
download Charter of services
Home
/
Sustainability
/
Hydrogen
/
Projects from the National Recovery and Resilience Plan (PNRR)
Projects from the National Recovery and Resilience Plan (PNRR)
The Autobrennero motorway, in view of the advanced planning already developed in this sector, was awarded 15 million in 2023 for the construction of four green hydrogen plants, out of a total of 64 million planned for all sites.
The four H2 centres, which will see the light of day by 2026, will be built at the Sadobre Truck Park in Sterzing, at the Paganella East and West service areas and at the Verona North Motorway Safety Centre (CSA). Initially they will be distribution-only plants and will be fuelled with hydrogen from Bolzano South. Once the demand for hydrogen gas exceeds 1,000 kg/day, a production plant will also be built in Vipiteno and Verona North. As the number of hydrogen vehicles in circulation increases, the plan will gradually be implemented with the other production and distribution plants in Sadobre, Nogaredo, Verona and Campogalliano.
The hydrogen plants will be supplied with hydrogen by means of replaceable tube trailers, containing a hydrogen quantity of about 1,000 kg at 380 bar. The dispensing and technological areas for hydrogen compression, metering and storage will be protected by a large canopy. To date, the company has drawn up the final design of the four sites and is in the process of obtaining the necessary administrative authorisations for their construction.
Project specifications from the National Recovery and Resilience Plan (PNRR)
- Plant at the Sadobre truck park (Sterzing)
The first distribution plant will be built at the Sadobre Truck Park in the municipality of Campo di Trens, in Vipiteno (BZ), adjacent to the existing fuel and natural gas (CNG and LNG) distribution plant.
Initially, in line with the objectives of the National Recovery and Resilience Plan (PNRR), only the distribution plant will be built, which should allow an average daily hydrogen refuelling of 2,000 kg.
Equipment included in the plant:
two boxes for tube trailers;
storage units (medium and high pressure tanks) capable of storing 2,000 kg of hydrogen;
compressors;
metering and control units;
cooling units;
four dispensing units for refuelling light (700 bar) and heavy (350 bar) vehicles.
The supply of hydrogen to the plant is provided by means of replaceable tube trailers. Subsequently, the plant will be supplied by a pipeline from the future hydrogen production area planned at a distance of about 700 m.
-
Plants at the Paganella East and West service areas
The second and third hydrogen distribution plants will be located at the Paganella East and Paganella West service areas in the municipality of Lavis (TN).
Both plants, for safety reasons, will be located opposite the traditional petroleum product distribution plants.
Equipment included in the plants:
one box for tube trailers;
storage units (medium and high pressure tanks) capable of storing 2,130 kg of hydrogen (Paganella East) and 2,400 kg (Paganella West);
compressors;
metering and control units;
cooling units;
four dispensing units for refuelling light (700 bar) and heavy (350 bar) vehicles.
-
Hydrogen distribution system at the Verona North Motorway Safety Centre
The fourth hydrogen distribution plant will be built in the municipality of Verona at the Verona North motorway station along a private access road to the Brenner Motorway Safety Centre.
Initially, in line with the objectives of the National Recovery and Resilience Plan (PNRR), only the distribution plant will be built, which should allow an average daily hydrogen refuelling of 3,500 kg.
Equipment included in the plant:
two boxes for tube trailers;
storage units (medium and high pressure tanks) capable of storing 3,500 kg of hydrogen;
compressors;
metering and control units;
cooling units;
three dispensing units for refuelling light (700 bar) and heavy (350 bar) vehicles.
The call for tenders for the contract for the executive design and construction of the hydrogen refuelling station in Verona Nord was published on 13 September 2024 and the deadline for submitting bids is
23 October 2024
.
Gallery
Upload Others
Service
Traveller
Traveller
HAULER
HAULER
Non-payment report
Toll: how is it calculated
Facilitations
Service Centres
Toll redund and billing
Electric mobility
Truck parks
Exceptional transport
Electrical charging points
Laundry service in Rovereto sud
De-icing system